Abbildungen der Seite
PDF
EPUB

lots other than those upon which the building was situated. Adams v. Central City Granite, etc. Co., 154 Mich. 448 (454-457), 117 N. W. 932.

The service of this statutory notice (p. 163) is designed to protect subcontractor, laborer, or materialman in case contractor's statement does not embody his claim. Smalley v. Ashland BrownStone Co., 114 Mich. 104 (108), 72 N. W. 29. Subcontractor's failure to serve statement on owner does not relieve owner from liability where he paid contractor in full without requiring sworn statement provided for by section 4 (C. L. 1915 §14799). Blitz v. Fields, 115 Mich. 675, 74 N. W. 186; Smalley v. Ashland BrownStone Co., 114 Mich. 104 (108), 72 N. W. 29; Green Bay Cut Stone Co. v. Fabry, 169 Mich. 544 (549), 135 N. W. 312. For form of this notice of furnishing, see Form No. 1 in Part II.

Owner not liable to lien claimants for greater amount than he contracted to pay original contractor and may set off damages for delay. Smalley v. Gearing, 121 Mich. 190 (197, 202, 205), 79 N. W. 1114, 80 N. W. 797; Wells v. Board of Education, 78 Mich. 270, 44 N. W. 267. After acceptance of building by owner as complying with contract, he cannot recoup against materialman for defects in construction. Hannah & Lay Co. v. Hartzell, 125 Mich. 177 (181), 84 N. W. 52. But mere taking possession cannot of itself be treated as unequivocal acceptance of performance. Gier v. Daiber, 148 Mich. 190 (193), 111 N. W. 773, Frohlich v. Klein, 160 Mich. 142, 125 N. W. 14. Where the contractor delayed performance and refused to proceed upon notice and the owner received bids and contracted with the lowest bidder for completion, in a proceeding by subcontractors to enforce a lien, held, the owner was entitled to offset against the

V.

original contractor or subcontractor the actual cost of completion, including sums necessarily paid for new plans. Yeomans Parker, 105 Mich. 323, 63 N. W. 316. It cannot be said that a particular course of construction is approved by owner because permitted by him without interference. Boots v. Steinberg, 100 Mich. 134 (137), 58 N. W. 657.

No lien is permitted where the contract was not performed according to its terms. Frohlich v. Klein, 160 Mich. 142, 125 N. W. 14; Evans v. Woodley, 173 Mich. 20, 138 N. W. 275. Abandonment by contractor does not preIclude liens of subcontractors and others to an aggregate which does not make the total cost exceed the contract price. Zilz v. Wilcox, 190 Mich. 486, 23 D. L. N. 24 (25), 157 N. W. 77; Delray Lumber Co. v. Keohane, 132 Mich. 17 (22), 92 N. W. 489.

The lien is direct in behalf of persons entitled and not by subrogation and claimant is not bound by stipulation as to acquisition of or waiving right to, lien in original contract to which he is not a party, except as to the contract price. Vaughan v. Ford. 162 Mich. 37 (45), 127 N. W. 280; Smalley v. Gearing, 121 Mich. 198, 79 N. W. 1114, 80 N. W. 797.

Payments by owner without requiring from contractor statement under section 4 are at owner's risk and his property is not relieved from lien because he believed that money previously advanced to materialmen on contractor's order paid them in full. Munroe v. Merrell, 113 Mich. 491, 71 N. W. 850. The owner is only entitled to protection as against persons unpaid, for such payments made without sworn statement as are distributed pro rata among all those entitled to participate. Fairbarn v. Moody, 116 Mich. 61, 74 N. W. 386, 75 Ñ. W. 469. See Vaughan v. Ford, 162 Mich. 37 (46), 127 N. W. 280. Though

payments by owner are founded on contractor's sworn statement, under section 4 (C. L. 1915 §14799), they must be distributed pro rata, among all claimants of whom he has notice, to protect against lien. Frohlich v. Carroll, 127 Mich. 562, 86 N. W. 1034. Payments without sworn statement, under section 4 (C. L. 1915 §14799), not distributed pro rata cannot be allowed in owner's favor as against materialman's lien. Greilick Co. v. Rogers, 144 Mich. 314 (317), 107 N. W. 885; Hannah & Lay Co. v. Hartzell, 125 Mich. 177 (180), 84 N. W. 52. The owner is relieved from liability to the extent to which his payments have been distributed among subcontractors, materialmen or laborers, though the money they received is not the identical money paid by owner to contractor. Where contractor furnishes materials, their value is to be included in determining amount distributed. Pro rata distribution among all claimants (of the same degree) is contemplated and owner is not entitled to credit for amount received by a claimant in excess of his proportionate share. Smalley Gearing, 121 Mich. 191 (199, 200, 201), 79 N. W. 1114, 80 N. W. 797. In determining cost of structure, in order to ascertain for what proportion of their claims claimants are entitled to liens, payments made without requiring statement from contractor, which went to pay for materials or labor actually going into the structure, are to be included. All lienor can claim is that the contract price (less any required deductions) be apportioned among those entitled and where cost of completed structure exceeds the contract price, a claimant is entitled to such proportion of his claim as the contract price bears

V.

to cost of completed structure. Godfrey Lumber Co. v. Cole, 151 Mich. 280, 114 N. W. 1018; Frchlish v. Ashton, 159 Mich. 265, 123 N. W. 1130. Balance remaining after allowing owner for payments properly distributed or made and ог damages deductions to which he may be entitled, if insufficient to pay claims in full, will be distributed among the claimants and unpaid claims, pro rata in proportion to the valid liens and other claims. Frohlich v. Ashton, 164 Mich. 132, (134), 129 N. W. 18; modifying same case in 159 Mich. 265, 123 N. W. 1130; Blitz v. Fields, 118 Mich. 85, 76 N. W. 118; Smalley v. Gearing, 121 Mich. 191, 79 N. W. 1114, 80 N. W. 797; Godfrey Lumber Co. v. Cole, 151 Mich. 280, 114 N. W. 1018; Kotcher v. Perrin, 149 Mich. 690, 113 N. W. 284. After the owner made payments to contractor without requiring statement under section 4 [C. L. 1915 (14799)], contractor abandoned his contract and owner completed the building. Held, the amounts paid by contractor to laborers and materialmen together with outstanding liens and cost of completion divided into the contract price, gives the per cent of his claim which each lienor is entitled to recover. Kotcher v. Perrin, 149 Mich. 690, 113 N. W. 284. Materialman receiving payments from contractor, while materials being furnished, who did not direct their application, had the right to apply them on charges other than those for materials entering into the building in question. Union Trust Co. v. Casserly, 127 Mich. 183, 86 N. W. 545; Grace Harbor Lumber Co. v. Ortman, 190 Mich. 429, 23 D. L. N. 73, (76), 157 N. W. 96; People v. Grant, 139 Mich. 26, 102 N. W. 226.

§ 104. Sec. 2. Lien on Property of Husband and Wife.

(Homesteads and estates by entirety.) In case the title to such lands upon which improvements are made is held by husband and wife jointly, or in case the lands upon which such improvements are made are held and occupied as a homestead, the lien given by this act shall attach to such lands and improvements if the improvements be made in pursuance of a contract in writing signed by both the husband and wife.

§2, as amended by Act 143 of 1897, C. L. 1915 (14797), How. 2nd Ed. §13767, C. L. 1897 (10711).

Mechanics' lien cannot be created against land held or being purchased to be held, in entirety by husband and wife, except under contract signed by both, nor has husband any interest therein during his lifetime to which lien can attach. Bauer v. Long, 147 Mich. 351, 110 N. W. 1059; McMillan v. Schneider, 147 Mich. 264, 110 N. W. 961; Restrick Lumber Co. v. Wyrembolski, 164 Mich. 71, 128 N. W. 1083; Sheldon, Kamm & Co., v. Bremer, 166 Mich. 578 (582), 132 N. W. 117; Burman v. Ewald, 192 Mich. 293 23 D. L. N. 449, 158 N. W. 853. The rule applies equally where the land is held by husband and wife under executory contract to purchase, and in the absence of wife's signature no lien attaches either to lot or structure. Frohlich v. Blackstock, 155 Mich. 604, 119 N. W. 906.

The constitution and statute prohibit lien attaching to homestead, unless arising under written contract signed by both husband and wife. Jossman v. Rice, 121 Mich. 270 (274-277), 80 N. W. 25; Burtch v. McGibbon, 98 Mich. 139, 56 N. W. 1110; John Wallace Sons Co. v. Wilkinson, 181 Mich. 693 (699), 148 N. W. 166; Holland Furnace Co. v. Hartig, 181 Mich. 342 (346), 148 N. W. 169.

The contract though in writing, must show intent to include the homestead interest to subject it to lien. Burtch v. McGibbon, 98 Mich. 139, 56 N. W. 1110; Hammond v. Wells, 45 Mich. 11, 7 N. W. 218. A homestead exemption may be claimed in land purchased for and upon which a homestead is to be constructed. Lamont v. LeFevre, 96 Mich. 175 (178), 55 N. W. 687; Deville v. Widoe, 64 Mich. 593 (594-595), 31 N. W. 533; Mills v. Hobbs, 76 Mich. 122 (125-126), 42 N. W. 1084, A contract for house to be used as homestead when completed must be signed by wife to give basis for lien upon the land,. though title in third person, though under section 3 lien may attach to house separately and be enforced by its sale and removal. Holliday v. Mathewson, 146 Mich. 336, 109 N. W. 669. The home

stead right is limited to premises actually occupied, where several dwellings are erected on one lot. Frohlich v. Carroll, 127 Mich. 562, 86 N. W. 1034. A homestead can be claimed if premises used partly for business purposes and partly as a dwelling. King v. Welborn, 83 Mich. 195 (197), 47 N. W. 106; Lamont v. LeFevre, 96 Mich. 175 (178), 55 N. W. 687. The excess over $1,500 may in certain cases be subject to lien, though wife does not sign contract. McAllister v. Des Rochers, 132 Mich. 382 (383-385), 93 N. W. 887; Scott v.

Keeth, 152 Mich. 547 (551-552), 116 N. W. 183; Lamont v. LeFevre, 96 Mich. 175 (176, 178), 55 N. W. 687. See, however, Holland Furnace Co. v. Hartig, 181 Mich. 342 (346-347), 148 N. W. 169. To reach the excess value of a homestead over $1,500, where it is subject to lien, the premises may be sold. Lamont v. LeFevre, 96 Mich. 175 (178), 55 N. W. 687; McAllister v. Des Rochers, 132

Mich. 381 (384), 93 N. W. 887. The ownership and occupancy of another house as a homestead held to preclude claim of homestead in house being constructed so as to defeat liens where wife did not sign. McMonegal v. Wilson, 103 Mich. 265 (267-268), 61 N. W. 495; Delray Lumber Co. v. Keohane, 132 Mich. 17 (19), 92 N. W. 489.

$105. Sec 3. Lien on Building.

(Liens where title not in contractee). Any person furnishing services or materials for the erection of a new building or structure upon land to which the person contracting for such erection has no legal title, shall have a lien therefore upon such building (buildings) or structure; and the forfeiture or surrender of any title or claim of title held by such contracting person to such land shall not defeat the lien upon such building or structure of such person furnishing services or materials as aforesaid.

(Liens on property held under land contract.) In case the property covered by the lien is held by the vendee in a land contract, and he surrenders or forfeits his rights. thereunder, the person or persons holding such liens may be subrogated to the rights of such vendee, as his rights existed immediately before such surrender or forfeiture, by performing the covenants contained in such contract within thirty days after such forfeiture or surrender is made.

§3, C. L. 1915 (14798), How. 2nd Ed. §13768, C. L. 1897 (10712).

This section does not apply and subject to lien a building erected upon land of the owner and wife as tenants in entirety, without a contract duly executed. Bauer v. Long, 147 Mich. 351, 110 N. W. 1059; Sheldon, Kamm & Co., v. Bremer, 166 Mich. 578, 132 N. W. 117. This section subjects the house, on land subject to home

stead claim where claimants of homestead have not the legal title, to lien, where wife does not sign contract and lien may be enforced by sale and removal of the house. Holliday v. Mathewson, 146 Mich. 336, 109 N. W. 669. But not so where the land is held by husband and wife under executory contract to purchase as tenants by entireties later converted into deed, and contract is signed only by husband. Frohlich v. Blackstock, 155

Mich. 604, 119 N. W. 906; John Wallace Sons Co. v. Wilkinson, 181 Mich. 694 (699), 148 N. W. 166. Where tenants by entireties executed a deed and took a land contract, the transaction amounting to a mortgage, it was held that they did not divest themselves of title so as to permit the

acquiring of lien against the building in a case where the wife did not sign, under the theory of erection of a new structure on land to which the person contracting had no legal title. Restrick Lumber Co. v. Wyrembolski, 164 Mich. 71, 128 N. W. 1083.

§ 106. Sec. 4. Owner May Retain Money.

(Right of owner to retain sums due contractor.) The owner, part owner or lessee may at any time retain from any moneys due or to become due to the original contractor, an amount sufficient to pay all demands owing or unpaid to any subcontractor, materialman or laborer, who has filed and served the notice in manner and form as provided in section one of this act.

(Statement by contractor.) The original contractor shall, whenever any payment of money shall become due from the owner, part owner or lessee, or whenever he desires to draw any money from the owner, part owner or lessee on such contract, make out and give to the owner, part owner or lessee, or his agent, a statement under oath of the number and names of every subcontractor or laborer in his employ, and of every person furnishing materials, giving the amount, if anything, which is due or to become due to them or any of them for work done or materials furnished, and

(Right of owner to retain sums due contractor.) The owner, part owner or lessee, or his agent, may retain out of any money then due or to become due to the contractor, an amount sufficient to pay all demands that are due or to become due to such subcontractors, laborers and materialmen, as shown by the contractor's statement, and pay the same to them according to their respective rights, and all payments so made shall, as between such owner, part owner or lessee, and such contractor, be considered the same as if paid to such original contractor.

« ZurückWeiter »