Abbildungen der Seite
PDF
EPUB

Opinion of the Court.

themselves, but as an action to recover the amount of the notes, by reason of a subsequent agreement of Cragin to pay them, the plaintiff fares no better. The only allegations touching the relation of Cragin to these notes are, that, in a suit by him against Fisk, he alleged that Fisk in purchasing the land acted merely as his agent, and that he owned the land and was liable and ready to pay for it; and that he was thereupon adjudged to be the owner of the land and took possession thereof. If this amounted to a promise to any one, it was not a promise to the plaintiff, nor even a promise to Fisk to pay to the plaintiff the amount of the notes, but it was, at the utmost, a promise to Fisk to pay that amount to him, or to indemnify him in case he should have to pay it. It is therefore not within the provisions of the Louisiana Codes, cited in argument; and the defendant is liable to an action at law by Fisk only, and not by the plaintiff. National Bank v. Grand Lodge, 98 U. S. 123; Exchange Bank v. Rice, 107 Mass. 37; M'Cauley v. Hagan, 6 Rob. La. 359. The final allegation, that by reason of the causes aforesaid, the defendant is indebted and liable to the plaintiff, is a mere conclusion of law, which is not admitted by demurrer or default. Hollis v. Richardson, 13 Gray, 392.

*

The judgment, having been rendered on default upon a declaration setting forth no cause of action, may be reversed on writ of error. McAllister v. Kuhn, 96 U. S. 87; Hollis v. Richardson, above cited; Louisiana Bank v. Senecal, 9 La. 225. This court, on reversing a judgment of the circuit court, may

*"A person may also, in his own name, make some advantage for a third person the condition or consideration of a commutative contract or onerous donation; and if such third person consents to avail himself of the advantage stipulated in his favor, the contract cannot be revoked." Louisiana Civil Code of 1870, art. 1890.

"An equitable action is that which does not immediately arise from a contract, but from equity in favor of a third person, not a party to it, and for whose benefit certain stipulations have been made; thus, if one stipulated in a contract entered into with another person, and as an express condition of that contract, that this person should pay a certain sum on his account, or give a certain thing to a third person, not a party to the act, that third person has an equitable action against the one who has contracted the obligation, to enforce the execution of the stipulation." Louisiana Code of Practice, art. 35.

Statement of Facts.

order such judgment for either party as the justice of the case may require. Rev. Stat. § 701; Insurance Cos. v. Boykin, 12 Wall. 433. In the case at bar, the order, following the precedent of Slacum v. Pomery, 6 Cranch, 221, will be that the judgment below be reversed, and the case remanded with directions that judgment be arrested.

Ordered accordingly.

UNITED STATES v. GIBBONS.

APPEAL FROM THE COURT OF CLAIMS.

Argued October 23d, 1883.-Decided November 12th, 1883.

Contract-Limitations.

1. Where the language of a contract is susceptible of two meanings, the court will infer the intention of the parties and their relative rights and obligations from the circumstances attending the transaction.

2. The parties contracted for the rebuilding of a shop at the Norfolk Navy Yard, which had been destroyed by fire. The specifications provided that "the foundation and the brick walls now standing that were uninjured by the fire will remain and will be carried up to the height designated in the plan by new work." After taking down so much of the old wall as was supposed to be injured, the government officers directed parties to examine the then condition of the walls before bidding on the specifications. Defendant in error did so, then bid, and his bid was accepted. Held, that the United States through its officers was bound to point out to bidders the parts of the walls which were to enter into the new structure, and that this was done by the act of dismantling a portion and leaving the rest of the wall to stand.

3. Payments under the contract were to be made in instalments and the balance when the work should be entirely completed. The contract also contemplated extra work. Held, that the cause of action for such extra work arose on the entire completion of the work.

The principal question in this case related to the proper construction of a building contract between the parties, entered into May 22d, 1866, the United States acting by Joseph Smith, chief of the bureau of yards and docks, under the authority of the Navy Department, for the repair of the entrance buildings and carpenter-shop at the Norfolk Navy Yard, which had been destroyed by fire in 1861, at the outbreak of the civil

war.

Statement of Facts.

The contract required the appellee to furnish, at his own risk and expense, all the materials and work necessary for the repairs of the buildings according to the plans and specifications annexed, the entrance buildings to be entirely completed and delivered within one hundred and twenty days, and the carpenter-shop within thirty days, from the date of the contract. A gross sum was to be paid for the work on each, partial payments to be made during the progress of the work upon the certificate of the superintendent, and final payment when the work should be entirely completed, according to the plans and specifications, "and to the satisfaction of the party of the second part." It was declared in the contract that "no extra charge for modifications will be allowed unless mutually agreed upon by the parties, and no changes or modifications mutually agreed upon by the parties to this contract shall in any way affect its validity."

The specifications for the entrance buildings contained the following clause, upon which the case turned:

"The foundations and the brick walls now standing that were uninjured by the fire will remain and be carried up to the height designated in the plan by new work."

The contract was made in pursuance of proposals, invited by an advertisement, in which it was stated that "persons desiring to bid must necessarily visit the yard and examine the present condition of the works, and can there see the plans and specifications to enable them to bid understandingly."

The findings of fact by the court of claims bearing on this point were as follows:

"III. At the outbreak of the late rebellion these buildings mentioned in the contract were burnt, but portions of the walls were left standing. Prior to the proposals for work, an inspection of these fragmentary walls, so left standing, had been made by the officers of the government in charge of the works, and those portions of them deemed unfit to form a part of the permanent structure were taken down, and those parts which were considered uninjured and proper to be built upon were left

Statement of Facts.

standing for that purpose. After the agents of the government had prepared the walls, retaining the portion which the civil engineer of the navy yard in charge of the work supposed might be used in the new structure, the chief of the bureau of yards and docks invited the examination of bidders by the advertisement annexed to the petition, and the claimant, by his agent, visited and saw the walls so standing. At the time the claimant, by his agent, so visited the yard he was shown the walls by a quarterman acting under the civil engineer of the yard. The claimant's agent asked if those walls were to stand. The quarterman replied that they were, so far as he knew, and that Mr. Williams, the master mason of the yard, and Mr. Worrall, the civil engineer of the yard, had said that they were to stand. (But it does not appear that the quarterman was authorized to make such representations to the claimant's agent.) And the civil engineer likewise represented to the claimant's agent that the portion of the walls then standing would remain and be used in the new work. After the claimant's agent had so visited the yard and been shown the walls, the claimant made his bid.

"IV. After the claimant had begun work under his contract, it was discovered that a portion of the walls still standing had been so injured by the fire as to be unfit for building a superstructure thereon. Commodore Hitchcock, commanding the naval station, thereupon ordered that the walls be further razeed, and pursuant to his orders, about one-third of the portion then standing was taken down by the claimant before proceeding to build. The effect of this second razeeing was that the claimant had to substitute new brick-work for that so removed; and the additional cost of construction thereby thrown upon him was the sum of $4,050; and for it he has received no remuneration additional to the price named or consideration expressed in the contract. It does not appear that at the time Commodore Hitchcock ordered the walls to be further razeed the defendants' officers made any pretence or claim that the increased expense was to be borne by the claimant as work required by the contract; nor does it appear that the claimant made any objection to the taking down of the walls as ordered by Commodore Hitchcock."

The appellee claimed compensation beyond the contract price

Opinion of the Court.

for the additional cost of construction rendered necessary by rebuilding that portion of the walls torn down by order of Commodore Hitchcock. The United States contended that it was covered by the terms of his contract.

Mr. Assistant Attorney-General Maury, for the appellant, cited Garrison v. United States, 7 Wall. 688; Chicago v. Sheldon, 9 Wall. 50, 54; Lowber v. Bangs, 2 Wall. 728, 737; Hawkins v. United States, 96 U. S. 689; and Dale v. United States, 14 Court Claims, 514.

Mr. Enoch Totten, for the appellee, cited Dermott v. Jones, 2 Wall. 1, 9, and the opinion of the court below in this case. MR. JUSTICE MATTHEWS delivered the opinion of the court. After stating the facts as above, he continued:

In our opinion the court of claims committed no error in allowing the claim of the contractor.

[ocr errors]

The language of the specifications is, perhaps, susceptible of two meanings. According to one, it is as if it read that "the foundations and the brick walls now standing," so far as they "were uninjured by the fire, will remain ;" according to the other, that "the foundations and brick walls now standing,' being such as "were uninjured by the fire, will remain." But, without going into any refinements of merely verbal interpretation, we think the meaning of the parties, explained by the circumstances attending the transaction, is sufficiently plain, and determine satisfactorily their relative rights and obligations.

It must be conceded, we think, that it was intended that the old portion of the work was to remain as part of the new structure only so far as it was in fact fit to do so, having reference to the character and uses of the building, and that the United States had the right to determine the fact of fitness. It was clearly its interest to do so, in advance of bidding, because if it reserved the right to make the determination at any stage in the progress of the work, or even at the time of final acceptance on its completion, the whole risk of the contingency would be thrown upon the contractor, who could only indemnify himself by an increase in the estimate of probable cost;

« ZurückWeiter »